870-2 Pump Station Replacement Project (P2083/P2562)

Reservoir

Click on image above to enlarge.

WHAT:

The project will replace the existing 870-1 High-Head and 571-1 Low-Head Pump Stations with a new pump station, including new recirculating pumps with chlorination injection capabilities.

The project will remove and replace the existing 571-1 Reservoir liner and cover with a new liner and cover, and also install new inlet/outlet piping for the reservoir.

571-1 Reservoir Capacity: 36.7 million gallons

WHERE:

Northeast corner of Otay Mesa. Existing 571-1 Reservoir and High Head/Low Head Pump Station site.

WHEN:

The construction Notice to Proceed was issued on July 27, 2017, and the project was accepted as complete by the District on August 25, 2021.

WHO:

Otay Water District and Pacific Hydrotech Corporation

WHY:

Replacement of aging infrastructure that is reaching the end of its useful life is critical to maintaining the District’s systems. Pump station replacement is standard maintenance that preserves the quality and safety of your water supply by maintaining the integrity and reliability of the pump stations. Customers save money over time when routine maintenance is performed on a regular basis.

Noise and traffic disruptions are not anticipated.

No water service disruptions are expected during the pump station replacement.

The final project cost is $ 22,559,243.11.

For additional information about the project, please contact the Engineering Manager Kevin Cameron at (619) 670-2248 or via e-mail at kcameron@otaywater.gov.